Time and Work PYQs for UPSC (2011-2024) | Solved Questions & PDF Download
Master Time and Work concepts for UPSC with solved Previous Year Questions (PYQs) from 2011 to 2024. This page provides detailed solutions, practice questions, and a free downloadable PDF to boost your UPSC preparation.
Why Time and Work Matters in UPSC?
This page provides year-wise solved questions to help you master this high-scoring topic.
Year-Wise Time and Work PYQs (2011-2024)
Q1. In a garrison, there was food for 1000 soldiers for one month. After 10 days, 1000 more soldiers joined the garrison. How long would the soldiers be able to carry on with the remaining food? [CSAT 2013]
(a) 25 days
(b) 20 days
(c) 15 days
(d) 10 days
Solution:
Given that,
In a garrison, there was food for 1000 soldiers for one month.
After 10 days, 1000 more soldiers joined the garrison.
Now,
Let suppose 1 soldier eats 1 part of food
1000 solders eat = 1000 x 1 = 1000 part per day
For a month total amount of food = 30 x 1000 = 30000 part
For 10 days soldier eat = 10 x 1000 = 10000 part of food
Remaining amount left = 30000 - 10000 = 20000 part of food
Thereafter 1000 soldiers more are added
Total soldiers = 2000
Food required per day = 2000 x 1 = 2000 part per day
Total number of days food can sustain = 20000/2000 = 10 days
Hence option (d) is correct
Q2. Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone? [CSAT 2016]
(a) 6 days
(b) 8 days
(c) 10 days
(d) 11 days
Solution:
Given that,
Ram and Shyam work on a job together for four days and complete 60% of it.
Ram takes leave then and Shyam works for eight more days to complete the job.
Now,
Let the work be W
Efficiency of Ram and Shyam be E1 and E2
Days taken to Complete whole work = 4 x (10/6) = 20/3
Remaining work = (E1 + E2) x 8/3 = E2 x 8
E1 = 2 x E2
E1 : E2 = 2 : 1
Ram can complete whole work in = [3 x (20/3)/2] = 10 days
Hence option (c) is correct
Q3. W can do 25% of a work in 30 days, X can do 1/4 of the work in 10 days, Y can do 40% of the work in 40 days and Z can do 1/3 of the work in 13 days. Who will complete the work first? [CSAT 2016]
(a) W
(c) Y
(b) X
(d) Z
Solution:
Given that,
W can do 25% of a work in 30 days
X can do 1/4 of the work in 10 days
Y can do 40% of the work in 40 days
Z can do 1/3 of the work in 13 days
Now,
Let the total work be a
W = 25% of a in 30 days
a/4 = 30 days
a = 120 days
X = a/4 of work in 10 days
a = 40 days
Y = 40% of a = 40 days
4a/10 = 40
a = 100 days
Z = 1/3 of a = 13 days
a = 39 days
Thus Z completes the work first
Hence option (d) is correct
Q4. P works thrice as fast as Q, whereas P and Q together can work four times as fast as R. If P, Q and R together work on a job, in what ratio should they share the earnings? [CSAT 2017]
(a) 3:1:1
(b) 3:2:4
(c) 4:3:4
(d) 3:1:4
Solution:
Given that,
P works thrice as fast as Q, whereas P and Q together can work four times as fast as R.
P, Q and R together work on a job
Now,
P = 3Q....(i)
P + Q = 4R.....(ii)
Thus, Q = R.....(iii)
So, P = 3R
Therefore the ratio = P : Q : R = 3 : 1 : 1
Hence option (a) is correct
Q5. A person X can complete 20% of work in 8 days and another person Y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?[CSAT 2020]
(a) 6
(c) 10
(b) 8
(d) 12
Solution:
Given that,
X can complete 20% of work in 8 days
Y can complete 25% of the same work in 6 days.
Now,
Let the total work be T
For X,
20% of T = T/5
Per day work done = (T/5)/8 = T/40
For Y
25% of T = T/4
Per day work done = (T/4)/6 = T/24
Working together = T/40 + T/24 = T/15 per day
So, 40% work can be completed in = (4T/10)/(T/15) = 6 days
Hence option (a) is correct
Q6. A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work is further increased by 50%? [CSAT 2021]
(a) 24
(b) 21
(c) 18
(d) 15
Solution:
Given that,
A man completes 7/8 of a job in 21 days.
Quantum of work is further increased by 50%
Now,
Time taken to complete the job = 21/7/8 = 24 days
Time to complete 50% of job = 24 x (50/100) = 12 days
Remaining work = 1 - 7/8 = 1/8
Time taken to complete 1/8 of work = 24 - 21 = 3
Number of days required = 12 + 3 = 15 days
Hence option (d) is correct
Q7. 24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work? [CSAT 2022]
(a) 30 days
(b) More than 30 days
(c) Less than 30 days or more than 30 days
(d) Data is inadequate to draw any conclusion
Solution:
Given that,
24 men and 12 women can do a piece of work in 30 days.
Now,
As there is no comparative analysis provided for men and women, thus time taken by 12 men and 24 women cannot be determined.
Hence option (d) is correct
Q8. A, B, C working independently can do a piece of work in 8, 16 and 12 days respectively. A alone works on Monday, B alone works on Tuesday, C alone works on Wednesday; A alone, again works on Thursday and so on. Consider the following statements: [CSAT 2023]
1. The work will be finished on Thursday.
2. The work will be finished in 10 days.
Which of the above statements is/are correct?
(a) 1 only
(c) Both 1 and 2
(b) 2 only
(d) Neither 1 nor 2
Solution:
Given that,
A, B, C working independently can do a piece of work in 8, 16 and 12 days respectively.
A alone works on Monday
B alone works on Tuesday
C alone works on Wednesday
A alone, again works on Thursday and so on.
Now,
LCM of 8,16 and 12 = 48
Total amount of work = 48
Thus,
Efficiency of A = 48/8 = 6 unit per day
Efficiency of B = 48/16 = 3 unit per day
Efficiency of C = 48/12 = 4 unit per day
Work done in 3 days = 6 + 3 + 4 = 13 units
Therefore, the cycle repeats in 3 days
So, 48/13 = 3 cycles and 9 units of work will remain
3 cycles = 3 x 3 = 9 days
Thus on the 10th day (Wednesday) A will work 6 units of work and on next day (Thursday) B will complete the remaining work which is on Thursday
1. The work will be finished on Thursday.
The work will be finished on Thursday by B
Hence statement 1 is correct
2. The work will be finished in 10 days.
Hence statement 2 is incorrect
Q9. A certain number of men can complete a piece of work in 6k days, where k is a natural number. By what percent should the number of men be increased so that the work can be completed in 5k days? [CSAT 2024]
(a) 10%
(b) (50/3)%
(c) 20%
(d) 25%
Solution:
Given that,
A piece of work that can be completed = 6k days, k is a natural number
Now,
Let number of men be M1 and M2
Days required to finish the work is D1 and D2
According to question the piece of work is same
So,
M1 x D1 = M2 x D2........(i)
As, D1 = 6k days and D2 = 5k days
M1 x 6k = M2 x 5k
(M1 x 6k)/5k = M2......(ii)
% change from M1 to M2 = {[(M1 x 6k)/5k]/ M1} x 100 = 120%
Thus % increase of men of M2 = 120 - 100 = 20 % more men are required to finish the task in 5k days
Hence option (c) is correct
10. X, Y and Z can complete a piece of work individually in 6 hours, 8 hours and 8 hours respectively. However, only one person at a time can work in each hour and nobody can work for two consecutive hours. All are engaged to finish the work. What is the minimum amount of time that they will take to finish the work? [CSAT 2024]
(a) 6 hours 15 minutes
(b) 6 hours 30 minutes
(c) 6 hours 45 minutes
(d) 7 hours
Solution:
Given that,
X, Y, Z can complete a piece of work in 6hr, 8hr, 8hr
No one works for two consecutive hours and only one person at a time can work in each hour
Now,
LCM of 6, 8 and 8 = 24
Total work unit = 24 units
So, X can complete a unit of work in an hour = 24/6 = 4 units/hr
Y can complete a unit of work in an hour = 24/8 = 3 units/hr
Z can complete a unit of work in an hour = 24/8 = 3 units/hr
Hours |
Unit of work |
1st hour |
X = 4 units |
2nd hour |
Y/Z = 3 units |
3rd hour |
X = 4 units |
4th hour |
Y/Z = 3 units |
5th hour |
X = 4 units |
6th hour |
Y/Z = 3 units |
Total work in 6 hours = 4 + 3 + 4 + 3 + 4 + 3 = 21units
Total work to complete = 24 units
Remaining work = 24 - 21 = 3 units
7th hour X will work
X work per min = 4/60 = 1/15 = 1 unit of work per 15 minutes
So, total time for 3 units = 45 min
X will complete remaining 3 units in 45 minutes
Total time taken = 6 hours 45 min
Hence option (c) is correct
ANSWER KEY
- 1. D
- 2. C
- 3. D
- 4. A
- 5. A
- 6. D
- 7. D
- 8. A
- 9. C
- 10. C
Download Time and Work PYQs PDF
- ➡️ Download the complete set of Time and Work PYQs (2011-2024) with solutions in PDF format.
- ➡️ Click Here to Download PDF
FAQs on Time and Work for UPSC
1. How important is Time and Work for UPSC CSAT?
➡️ Extremely important - typically 2-3 questions appear every year in CSAT Paper II.
2. What's the best approach to solve Time and Work problems?
- ➡️ Convert all work to work/day rates
- ➡️ Use LCM method for complex problems
- ➡️ Practice worker addition/removal scenarios
3. Any shortcut formulas to remember?
➡️ If A’s rate=1x,B’s rate=1yCombined time=xyx+yIf A’s rate=x1,B’s rate=y1Combined time=x+yxy
Conclusion
Mastering Time and Work PYQs gives you an edge in UPSC CSAT. This page provides:
✅ Year-wise solved questions (2011-2024)
✅ PDF download of all PYQs
✅ Efficiency-boosting strategies
For more UPSC resources, visit iassetu.com.
Internal Links:
Related Links:
- Analytical Reasoning PYQ's
- Arithmetic & Geometric Progression PYQ
- Average PYQs for UPSC
- Blood Relation PYQ's
- Boats & Streams PYQ's
- Calendar PYQs for UPSC (2011-2024)
- Clock PYQs for UPSC (2011-2024)
- Coding Decoding PYQs for UPSC (2011-2024)
- Continuous Series PYQ
- Cube and Dice PYQ
- Data Interpretation PYQs for UPSC (2011-2024)
- Direction Sense PYQ's
- General Mental Ability PYQs for UPSC (2011-2024)
- Geometry & Mensuration PYQs for UPSC (2011-2024)
- Insert the Missing Character PYQs for UPSC (2011-2024)
- Mixture & Alligation PYQ's
- Mixture & Alligation PYQs for UPSC (2011-2024)
- Number Ranking & Sequence PYQs for UPSC
- Number Series PYQs for UPSC
- Number System PYQs for UPSC (2011-2024) | Solved Questions & PDF
- Partnership PYQs for UPSC (2011-2024) | Solved Questions & PDF Download
- Percentage PYQ's
- Pipes and Cisterns PYQs for UPSC (2011-2024)
- Probability PYQs for UPSC (2011-2024)
- Problems on Ages PYQs
- Profit and Loss PYQs for UPSC (2011-2024)
- Ratio & Proportion PYQs for UPSC
- Seating Arrangement PYQs
- Time, Speed & Distance PYQs for UPSC
- Trains Problems PYQs
- Venn Diagrams PYQs for UPSC (2011-2024)
- PDF's & Booklets
- UPSC Previous Year Question Papers
- IAS Salary 2025, Pay Scale, Perks, Allowances & Career Growth